Traffic & Parking Logistics Alerts

As the Hartwick Drive and Campus Gateway construction and paving continues, stay safe and use caution around work zones.

Today’s Alert: 08/18/17 Friday 5:00 p.m.

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano Hall. That area is for construction vehicles.
  • All College and Aramark employees are reminded to use extra caution when walking in the vicinity of these areas and to be diligent not to walk through construction zones.
  • Guests visiting the College are also advised to use extra caution around construction zones.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.
All milling and paving work is weather permitting. 
Please avoid designated areas on paving days.

  • To access Dewar Hall from Clark Hall, use the new steps between Clark Hall and Shineman Chapel House down to the Hartwick Drive walk. Please be sure to stay in the cordoned off area that will be marked with tape and barrels to guide you to the Dewar Hall Bookstore entrance. 
  • Do not walk while using ear buds (head phones) around work zones.
  • Please use caution in the construction zone.

Please note that the work schedule remains weather and equipment dependent.

Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

Campus Map


Past Alerts 

08/16/17: Wednesday

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano Hall. That area is for construction vehicles.
  • All College and Aramark employees are reminded to use extra caution when walking in the vicinity of these areas and to be diligent not to walk through construction zones.
  • Guests visiting the College are also advised to use extra caution around construction zones.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.
All milling and paving work is weather permitting. 
Please avoid designated areas on paving days.

  • Speed bump installation will be done on Monday, August 14 from Shineman Chapel House to Binder Physical Education Center. Access Binder (PEC) at Clinton Street and “wrong way” past the New Residence Hall.
  • Hartwick Drive will closed at Shineman corner and entrance to Clark/ Bresee on Monday, August 14. Access to Saxton Hall, Perrella Health Center, Holmes Hall, and Shineman lots will not be affected. Deliveries and ADA access to Clark/ Bresee may experience delays.
  • Access to Yager Hall patio will be closed Monday, August 14-Friday, August 18 to resurface the patio and grout the granite steps. Enter and exit Yager Hall though the Museum entrance or the Slade Theatre entrance.
  • Saxton Hall parking lot and the road from Binder lot to the new apartment community building will be paved Thursday, August 17th. No parking in the Saxton lot or the road from upper binder after Wednesday, August 16 5 p.m. 
  • Effective Thursday, August 3 after 3 p.m., the valley side (East) entrance/exit to Clark Hall will be closed to facilitate construction for the new walk. 
  • Effective Wednesday, August 16 after 12 p.m. the Shineman Chapel House side (North) Clark Hall entrance/exit will be closed to facilitate reconstruction of the sidewalk. Please use the back (West) entrance/exit to Clark Hall on the second floor.
  • To access Dewar Hall from Clark Hall, use the new steps between Clark Hall and Shineman Chapel House down to the Hartwick Drive walk. These steps will have wood hand rails temporarily installed. Please be sure to stay in the cordoned off area that will be marked with tape and barrels to guide you to the Dewar Hall Bookstore entrance. 
  • Do not walk while using ear buds (head phones) around work zones.
  • Please use caution in the construction zone.

 

08/14/17: Monday 8:30 a.m. 

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano Hall. That area is for construction vehicles.
  • All College and Aramark employees are reminded to use extra caution when walking in the vicinity of these areas and to be diligent not to walk through construction zones.
  • Guests visiting the College are also advised to use extra caution around construction zones.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.
All milling and paving work is weather permitting. 
Please avoid designated areas on paving days.

  • Speed bump installation will be done on Monday, August 14 from Shineman Chapel House to Binder Physical Education Center. Access Binder (PEC) at Clinton Street and “wrong way” past the New Residence Hall.
  • Hartwick Drive will closed at Shineman corner and entrance to Clark/ Bresee on Monday, August 14. Access to Saxton Hall, Perrella Health Center, Holmes Hall, and Shineman lots will not be affected. Deliveries and ADA access to Clark/ Bresee may experience delays.
  • Access to Yager Hall patio will be closed Monday, August 14-Friday, August 18 to resurface the patio and grout the granite steps. Enter and exit Yager Hall though the Museum entrance or the Slade Theatre entrance.
  • Effective Thursday, August 3 after 3 p.m., the valley side (East) entrance/exit to Clark Hall will be closed to facilitate construction for the new walk. The Shineman Chapel House side (North) Clark Hall entrance/exit should be utilized.
  • To access Dewar Hall from Clark Hall, use the new steps between Clark Hall and Shineman Chapel House down to the Hartwick Drive walk. These steps will have wood hand rails temporarily installed. Please be sure to stay in the cordoned off area that will be marked with tape and barrels to guide you to the Dewar Hall Bookstore entrance. 
  • Do not walk while using ear buds (head phones) around work zones.
  • Please use caution in the construction zone.

08/11/17: Friday 8:30, 10:30 a.m. & 1:15 p.m.

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano Hall. That area is for construction vehicles.
  • All College and Aramark employees are reminded to use extra caution when walking in the vicinity of these areas and to be diligent not to walk through construction zones.
  • Guests visiting the College are also advised to use extra caution around construction zones.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.
All milling and paving work is weather permitting. 
Please avoid designated areas on paving days.

  • Due to the potential for rain, paving the south side of Hartwick Drive has begun this afternoon, Friday, August 11. One lane will be kept open to reduce congestion.
  • Hartwick Drive main entrance to Shineman Chapel House, including Saxton Hall Parking Lot, will be closed for paving on Saturday, August 12. No entry except construction vehicles during paving.
  • Please enter campus from Clinton Street, access to Binder Physical Education Center and Faculty & Staff parking between Wright Stadium and Binder (PEC), through Miller Parking Lot and wrong way past the new residence hall.
  • Parking for Johnstone Science Center, Golisano, Bresee, Clark, and Dewar Halls use Miller Parking Lot.
  • Access to Yager Hall patio will be closed Monday, August 14-Friday, August 18 to resurface the patio and grout the granite steps. Enter and exit Yager Hall though the Museum entrance or the Slade Theatre entrance.
  • Effective Thursday, August 3 after 3 p.m., the valley side (East) entrance/exit to Clark Hall will be closed to facilitate construction for the new walk. The Shineman Chapel House side (North) Clark Hall entrance/exit should be utilized.
  • To access Dewar Hall from Clark Hall, use the new steps between Clark Hall and Shineman Chapel House down to the Hartwick Drive walk. These steps will have wood hand rails temporarily installed. Please be sure to stay in the cordoned off area that will be marked with tape and barrels to guide you to the Dewar Hall Bookstore entrance. 
  • Do not walk while using ear buds (head phones) around work zones.
  • Please use caution in the construction zone.

08/09/17: Wednesday 2:00 p.m.

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano Hall. That area is for construction vehicles.
  • All College and Aramark employees are reminded to use extra caution when walking in the vicinity of these areas and to be diligent not to walk through construction zones.
  • Guests visiting the College are also advised to use extra caution around construction zones.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.
All milling and paving work is weather permitting. 
Please avoid designated areas on paving days.

  • As of 1:30 p.m. on Wednesday, August 9, paving has begun at west side of the Johnstone Science Center (JSC). Do not use Hartwick College Center for Craft Food & Beverage or Greenhouse west (hillside) entrance or exit for the next 6 hours. All JSC foot traffic enter through JSC main entrance at the patio, south end facing the valley or  through 1st floor entrance facing Van Ess Hall.
  • Hartwick Drive main entrance to Shineman Chapel House including Saxton Parking Lot will be milled Thursday, August 10. No entry except construction vehicles during milling.
  • Please enter campus from Clinton Street, access to Binder Physical Education Center and Faculty & Staff parking between Wright Stadium and Binder (PEC), through Miller Parking Lot and wrong way past the new residence hall.
  • Parking for Johnstone Science Center, Golisano, Bresee, Clark, and Dewar Halls use Miller Parking Lot.
  • Access to Shineman Parking Lot will be limited as the milling machine will require 3 passes on Hartwick Drive. No entrance or egress near milling operation.
  • ADA, service vehicles and deliveries to Clark/Bresee Halls use same route, but be prepared to stop if milling is in progress at that end.
  • Hartwick Drive and Saxton Hall Parking Lot will be paved with the base layer on Saturday, August 12, same driving and parking restrictions apply.
  • No paving work is scheduled for Friday, August 11.
  • Parking lot striping is scheduled to begin Thursday, August 10 at 2 a.m. Lot striping should be finished by Thursday afternoon. Please no parking in following lots Wednesday (8/9/17 night: Hilltop/Oyaron Houses- (residents park in large lot, Miller Lot), Lower Yager Hall Lot, Wilder Hall Lot, VanEss Hall Lot, Leitzell Hall Lot, and Upper Perrella Health Center Lot.
  • As of Tuesday, August 8, paving has begun from Wright Stadium to Binder Physical Education Center (PEC), upper Binder parking lot is swept and ready for paving on August 9.
  • Please no parking at upper Binder parking lot. Access Binder (PEC) through the Miller parking lot next to Johnstone Science Center (JSC) and up the ” wrong way” past the new residence hall.
  • Parking is now open at Miller Court and next to Elmore Field.
  • As of Wednesday, August 9, access Miller Court normally but you will also need to exit campus the wrong way towards Shineman Chapel House as upper Binder PEC parking lot is paved.
  • Effective Thursday, August 3 after 3 p.m., the valley side (East) entrance/exit to Clark Hall will be closed to facilitate construction for the new walk. The Shineman Chapel House side (North) Clark Hall entrance/exit should be utilized.
  • To access Dewar Hall from Clark Hall, use the new steps between Clark Hall and Shineman Chapel House down to the Hartwick Drive walk. These steps will have wood hand rails temporarily installed. Please be sure to stay in the cordoned off area that will be marked with tape and barrels to guide you to the Dewar Hall Bookstore entrance. 
  • Hartwick Drive demo and reconstruction continues.
  • Beginning Friday, June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Do not walk while using ear buds (head phones) around work zones.
  • Please use caution in the construction zone.

08/07/17: Tuesday 9:00 a.m., updated 2:45 p.m.

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano Hall. That area is for construction vehicles.
  • All College and Aramark employees are reminded to use extra caution when walking in the vicinity of these areas and to be diligent not to walk through construction zones.
  • Guests visiting the College are also advised to use extra caution around construction zones.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.
All milling and paving work is weather permitting. 
Please avoid designated areas on paving days.

  • Hartwick Drive main entrance to Shineman Chapel House including Saxton Parking Lot will be milled Thursday, August 10. No entry except construction vehicles during milling.
  • Please enter campus from Clinton Street, access to Binder Physical Education Center and Faculty & Staff parking between Wright Stadium and Binder (PEC), through Miller Parking Lot and wrong way past the new residence hall.
  • Parking for Johstone Science Center, Golisano, Bresee, Clark, and Dewar Halls use Miller Parking Lot.
  • Access to Shineman Parking Lot will be limited as the milling machine will require 3 passes on Hartwick Drive. No entrance or egress near milling operation.
  • ADA, service vehicles and deliveries to Clark/Bresee Halls use same route, but be prepared to stop if milling is in progress at that end.
  • Hartwick Drive and Saxton Hall Parking Lot will be paved with the base layer on Saturday, August 12, same driving and parking restrictions apply.
  • No paving work is scheduled for Friday, August 11.
  • Parking lot striping is scheduled to begin Thursday, August 10 at 2 a.m. Lot striping should be finished by Thursday afternoon. Please no parking in following lots Wednesday (8/9/17 night: Hilltop/Oyaron Houses- (residents park in large lot, Miller Lot), Lower Yager Hall Lot, Wilder Hall Lot, VanEss Hall Lot, Leitzell Hall Lot, and Upper Perrella Health Center Lot.
  • As of Tuesday, August 8, paving has begun from Wright Stadium to Binder Physical Education Center (PEC), upper Binder parking lot is swept and ready for paving on August 9.
  • Please no parking at upper Binder parking lot. Access Binder (PEC) through the Miller parking lot next to Johnstone Science Center (JSC) and up the ” wrong way” past the new residence hall.
  • Parking is now open at Miller Court and next to Elmore Field.
  • As of Wednesday, August 9, access Miller Court normally but you will also need to exit campus the wrong way towards Shineman Chapel House as upper Binder PEC parking lot is paved.
  • Effective Thursday, August 3 after 3 p.m., the valley side (East) entrance/exit to Clark Hall will be closed to facilitate construction for the new walk. The Shineman Chapel House side (North) Clark Hall entrance/exit should be utilized.
  • To access Dewar Hall from Clark Hall, use the new steps between Clark Hall and Shineman Chapel House down to the Hartwick Drive walk. These steps will have wood hand rails temporarily installed. Please be sure to stay in the cordoned off area that will be marked with tape and barrels to guide you to the Dewar Hall Bookstore entrance. 
  • Hartwick Drive demo and reconstruction continues.
  • Beginning Friday, June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Do not walk while using ear buds (head phones) around work zones.
  • Please use caution in the construction zone.

08/03/17: Thursday 2:50 p.m.

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano Hall. That area is for construction vehicles.
  • All College and Aramark employees are reminded to use extra caution when walking in the vicinity of these areas and to be diligent not to walk through construction zones.
  • Guests visiting the College are also advised to use extra caution around construction zones.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.
All milling and paving work is weather permitting. 
Please avoid designated areas on paving days.

  • The section of road from the Binder Physical Education Center parking lot (just past the tennis court access road by the metal guard rails) to the corner of the New Residence Hall and Oyaron House will be closed Thursday, August 3 – Friday, August 4. The New Residence Hall, Oyaron and Hilltop Houses can still be accessed from the lower campus. The upper campus traffic will need to exit going back down the hill past Wright Stadium. Please use extreme caution when exiting as on coming traffic may be encountered. Expectations are that the closed section will reopen mid to late afternoon.
  • Effective Thursday, August 3 after 3 p.m., the valley side (East) entrance/exit to Clark Hall will be closed to facilitate construction for the new walk. The Shineman Chapel House side (North) Clark Hall entrance/exit should be utilized.
  • To access Dewar Hall from Clark Hall, use the new steps between Clark Hall and Shineman Chapel House down to the Hartwick Drive walk. These steps will have wood hand rails temporarily installed. Please be sure to stay in the cordoned off area that will be marked with tape and barrels to guide you to the Dewar Hall Bookstore entrance. 
  • Lower Yager Hall parking lot and road to Wilder Hall paving is complete. Area is still closed to allow the material to harden.
  • Access upper Yager Hall parking lot at Seneca Lane (Willis Street) by facilities and enter Yager Hall parking lot from the Smith Hall end. Please use caution as this will be a two way entrance / exit.
  • Base layer will be applied at Miller Lot midweek.
  • Traffic will be diverted through Miller Lot while milling and green space construction is under way at the New Residence Hall.
  • Hartwick Drive demo and reconstruction continues.
  • Saxton Hall and Wilder Hall refurbishment complete. Furniture to be delivered.
  • Beginning Friday, June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Do not walk while using ear buds (head phones) around work zones.
  • Please use caution in the construction zone.

 

08/03/17: Thursday 8:20 a.m.

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano Hall. That area is for construction vehicles.
  • All College and Aramark employees are reminded to use extra caution when walking in the vicinity of these areas and to be diligent not to walk through construction zones.
  • Guests visiting the College are also advised to use extra caution around construction zones.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.
All milling and paving work is weather permitting. 
Please avoid designated areas on paving days.

  • The section of road from the Binder Physical Education Center parking lot (just past the tennis court access road by the metal guard rails) to the corner of the New Residence Hall and Oyaron House will be closed for most of the morning of Wednesday, August 3. The New Residence Hall, Oyaron and Hilltop Houses can still be accessed from the lower campus. The upper campus traffic will need to exit going back down the hill past Wright Stadium. Please use extreme caution when exiting as on coming traffic may be encountered. Expectations are that the closed section will reopen mid to late afternoon.
  • Effective Friday August 4, the valley side (East) entrance/exit to Clark Hall will be closed to facilitate construction for the new walk. The Shineman Chapel House side (North) Clark Hall entrance/exit should be utilized.
  • To access Dewar Hall from Clark Hall, use the new steps between Clark Hall and Shineman Chapel House down to the Hartwick Drive walk. These steps will have wood hand rails temporarily installed. Please be sure to stay in the cordoned off area that will be marked with tape and barrels to guide you to the Dewar Hall Bookstore entrance. 
  • Lower Yager Hall parking lot and road to Wilder Hall paving is nearly complete. The road will be closed to allow the material to harden.
  • Access upper Yager Hall parking lot at Seneca Lane (Willis Street) by facilities and enter Yager Hall parking lot from the Smith Hall end. Please use caution as this will be a two way entrance / exit while lower Yager and Wilder areas are top paved.
  • Base layer will be applied at Miller Lot midweek.
  • Milling will be done at the upper Perrella Health Center parking lot and the road in front of the New Residence Hall.
  • Traffic will be diverted through Miller Lot while milling and green space construction is under way at the New Residence Hall.
  • Hartwick Drive demo and reconstruction continues.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Beginning Friday, June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • Installation of a walkway from upper Binder Physical Education Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.
  • Please use caution in the construction zone.

8/02/17: Wednesday

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano Hall. That area is for construction vehicles.
  • All College and Aramark employees are reminded to use extra caution when walking in the vicinity of these areas and to be diligent not to walk through construction zones.
  • Guests visiting the College are also advised to use extra caution around construction zones.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.
All milling and paving work is weather permitting. 
Please avoid designated areas on paving days.

  • Effective Friday August 4, the valley side (East) entrance/exit to Clark Hall will be closed to facilitate construction for the new walk. The Shineman Chapel House side (North) Clark Hall entrance/exit should be utilized.
  • To access Dewar Hall from Clark Hall, use the new steps between Clark Hall and Shineman Chapel House down to the Hartwick Drive walk. These steps will have wood hand rails temporarily installed. Please be sure to stay in the cordoned off area that will be marked with tape and barrels to guide you to the Dewar Hall Bookstore entrance. 
  • Lower Yager Hall parking lot and road to Wilder Hall paving is nearly complete. The road will be closed to allow the material to harden.
  • Access upper Yager Hall parking lot at Seneca Lane (Willis Street) by facilities and enter Yager Hall parking lot from the Smith Hall end. Please use caution as this will be a two way entrance / exit while lower Yager and Wilder areas are top paved.
  • Base layer will be applied at Miller Lot midweek.
  • Milling will be done at the upper Perrella Health Center parking lot and the road in front of the New Residence Hall.
  • Traffic will be diverted through Miller Lot while milling and green space construction is under way at the New Residence Hall.
  • Hartwick Drive demo and reconstruction continues.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Beginning Friday, June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • Installation of a walkway from upper Binder Physical Education Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.
  • Please use caution in the construction zone.

08/01/17: Tuesday

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano Hall. That area is for construction vehicles.
  • All College and Aramark employees are reminded to use extra caution when walking in the vicinity of these areas and to be diligent not to walk through construction zones.
  • Guests visiting the College are also advised to use extra caution around construction zones.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.
All milling and paving work is weather permitting. 
Please avoid designated areas on paving days.

  • Lower Yager Hall parking lot and road to Wilder Hall paving is nearly complete. The road will be closed to allow the material to harden.
  • Access upper Yager Hall parking lot at Seneca Lane (Willis Street) by facilities and enter Yager Hall parking lot from the Smith Hall end. Please use caution as this will be a two way entrance / exit while lower Yager and Wilder areas are top paved.
  • Upper and lower Smith Hall and Townhouses roadway and parking areas will be paved Tuesday, August 1.
  • Base layer will be applied at Miller Lot midweek.
  • Milling will be done at the upper Perrella Health Center parking lot and the road in front of the New Residence Hall.
  • Traffic will be diverted through Miller Lot while milling and green space construction is under way at the New Residence Hall.
  • Hartwick Drive demo and reconstruction continues.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Beginning Friday, June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • Installation of a walkway from upper Binder Physical Education Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.

07/31/17: Monday

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano Hall. That area is for construction vehicles.
  • All College and Aramark employees are reminded to use extra caution when walking in the vicinity of these areas and to be diligent not to walk through construction zones.
  • Guests visiting the College are also advised to use extra caution around construction zones.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.
All milling and paving work is weather permitting. 
Please avoid designated areas on paving days.

  • Anderson Center for the Arts (ACA) parking is accessible off Clinton Street at ACA.
  • The road from Wilder Hall to Anderson Center for the Arts and Clinton Street will be top paved on Monday, July 31.
  • Access upper Yager Hall parking lot at Seneca Lane (Willis Street) by facilities and enter Yager Hall parking lot from the Smith Hall end. Please use caution as this will be a two way entrance / exit while lower Yager and Wilder areas are top paved.
  • Top paving of Townhouses will begin on Monday, July 31.
  • Hartwick Drive demo and reconstruction continues.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Beginning Friday, June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • Installation of a walkway from upper Binder Physical Education Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.

07/27/17: Thursday

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano Hall. That area is for construction vehicles.
  • All College and Aramark employees are reminded to use extra caution when walking in the vicinity of these areas and to be diligent not to walk through construction zones.
  • Guests visiting the College are also advised to use extra caution around construction zones.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.
All milling and paving work is weather permitting. 
Please avoid designated areas on paving days.

  • The large lot at lower Yager Hall will be paved on Saturday, July 29.
  • Road from Clinton Street past Anderson Center for the Arts (ACA) and the small lot across from ACA will be closed for paving on Saturday, July 29. Road and Lot will be closed to all traffic until Monday, July 31
  • To access ACA this weekend, please park on Clinton Street or in the upper Yager Hall parking lot. 
  • Use the Seneca Lane (Willis Street) by facilities entrance on Clinton Street to enter south end of campus.
  • The road from Wilder Hall to Anderson Center for the Arts and Clinton Street will be top paved on Monday, July 31.
  • Hartwick Drive demo and reconstruction continues.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Beginning Friday, June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • Installation of a walkway from upper Binder Physical Education Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano Hall. That area is for construction vehicles.
  • All College and Aramark employees are reminded to use extra caution when walking in the vicinity of these areas and to be diligent not to walk through construction zones.
  • Guests visiting the College are also advised to use extra caution around construction zones.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.
All milling and paving work is weather permitting. 
Please avoid designated areas on paving days.

  • Top paving of the walkway from the Dewar Union entrance to VanEss Hall will be done Friday, July 28.
  • The large lot at lower Yager Hall will be paved on Saturday, July 29.
  • The road from Wilder Hall to Anderson Center for the Arts and Clinton Street will be top paved on Monday, July 31.
  • Hartwick Drive demo and reconstruction continues.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Beginning Friday, June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • Installation of a walkway from upper Binder Physical Education Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.

07/26/17: Wednesday: 8:45 a.m.

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano Hall. That area is for construction vehicles.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.
All milling and paving work is weather permitting.

  • Iroquois Drive between Townhouses and Smith Hall will be temporarily closed to through traffic on Wednesday, July 26. This closure is necessary in order to replace a culvert that runs diagonally under the road surface. To access Smith Hall please use the lower route. To access Town House please use the upper route.
  • Hartwick Drive demo and reconstruction continues.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Beginning Friday, June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • Installation of a walkway from upper Binder Physical Education Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.

07/21/17: Friday: 3:30 p.m.

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano Hall. That area is for construction vehicles.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.
All milling and paving work is weather permitting.

  • Paving continues at Seneca Lane (road off Clinton Street between Anderson Center for the Arts and Facilities), and the road from Smith Hall and Townhouses to Johnstone Science Center on Friday, July 21. One lane will remain open while paving is in progress. Use caution and be prepared for potential delays.
  • Rebuilding of Memorial Staircase steps and wall will begin Monday-Tuesday, July 23-24.
  • Top paving the walkway from Dewar Hall to Leitzell Hall will begin Monday-Tuesday, July 23-24.
  • Top paving Leitzell Hall and VanEss Hall parking lot/road will begin Monday-Tuesday, July 23-24.
  • Milling from upper Binder parking lot to New Residence Hall may begin Monday-Tuesday, July 23-24. Please no parking along this route. Expect delays due to milling. Hilltop/Oyaron residents may park on far south end of Miller parking lot during milling.
  • Hartwick Drive demo and reconstruction continues.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Beginning Friday, June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • Installation of a walkway from upper Binder Physical Education Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.

07/21/17: Friday: 8:30 a.m.

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano. That area is for construction vehicles.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.

  • Weather permitting, paving will continue at Seneca Lane (road off Clinton Street between Anderson Center for the Arts and Facilities), and the road from Smith Hall and Townhouses to Johnstone Science Center on Friday, July 21. One lane will remain open while paving is in progress. Use caution and be prepared for potential delays.
  • The base layer at Binder Physical Education Center will be applied either late Thursday, July 20 or in the morning of Friday, July 21.
  • Hartwick Drive demo and reconstruction continues.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Beginning Friday, June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • Installation of a walkway from upper Binder Physical Education Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.

07/19/17: Wednesday

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano. That area is for construction vehicles.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.

  • Weather permitting, milling will begin on the road from the lower Yager Hall parking lot, past Smith Hall and Townhouses to Johnstone Science Center on Thursday, July 20.
  • The base layer at Binder Physical Education Center will be applied either late Thursday, July 20 or in the morning of Friday, July 21.
  • If the weather continues to be favorable, the top layer of pavement will be applied to roadway at Hilltop & Oyaron Houses and Townhouses.
  • Hartwick Drive demo and reconstruction continues.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Beginning Friday, June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • Installation of a walkway from upper Binder PE Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.

07/17/17: Monday

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano. That area is for construction vehicles.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.

  • Weather permitting, paving the road and parking areas from Johnstone Science Center patio to the Greenhouse will be begin Monday, July 17. Please do not park in this area and be aware of increased construction activity.
  • The walk from Dewar Union to Lietzell Hall, Yager Slade Theater (both exits), Leitzell Hall and VanEss Hall will be paved on Tuesday, July 18.
  • The road way to Hilltop and Oyaron Houses will be paved on Wednesday, July 19.
  • Hartwick Drive demo and reconstruction continues.
  • Bricks are being installed on the Campus Gateway signs at West Street. Power has been run to the large wall on West Street.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Beginning Friday June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • The townhouse sidewalks will be finished.
  • Installation of a walkway from upper Binder PE Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.

07/13/17: Thursday

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano. That area is for construction vehicles.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.

  • Weather permitting, milling the road and parking areas from Johnstone Science Center patio to the Greenhouse will be done Saturday, July 15. Please do not park in this area and be aware of increased construction activity.
  • Hartwick Drive demo and reconstruction continues.
  • Bricks are being installed on the Campus Gateway signs at West Street. Power has been run to the large wall on West Street.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Beginning Friday June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • The townhouse sidewalks will be finished.
  • Installation of a walkway from upper Binder PE Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.

 

07/10/17: Monday

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano. That area is for construction vehicles.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.

  • Milling from Wilder Hall to lower Yager Hall parking lot will take place Monday, July 10. Enter Yager Hall from Smith Hall end of the parking lot.
  • Hartwick Drive demo continues.
  • Bricks are being installed on the Campus Gateway signs at West Street. Power has been run to the large wall on West Street.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Parking lot between Johnstone Science Center and Hilltop/ Oyaron Houses will be milled in its entirety. Please no parking, residents may park at upper Binder PE Center lot.
  • Beginning Friday June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • The townhouse sidewalks will be finished.
  • Installation of a walkway from upper Binder PE Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.

07/05/17: Wednesday

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano. That area is for construction vehicles.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.

  • The Townhouse road will be milled Thursday 7/6/17, please be alert for increased construction activity between Johnston Science Center and Smith Hall.
  • Weather permitting roads and lots to be milled this week.
  • Hartwick Drive demo continues.
  • Bricks are being installed on the Campus Gateway signs at West Street. Power has been run to the large wall on West Street.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Work on Yager Hall Patio retaining walls to run June 19-July 3.
  • Parking lot between Johnstone Science Center and Hilltop/ Oyaron Houses will be milled in its entirety. Please no parking, residents may park at upper Binder PE Center lot.
  • Beginning Friday June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • The townhouse sidewalks will be finished.
  • Installation of a walkway from upper Binder PE Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.