Today’s Alert: 06/26/17 Monday 3:30 p.m.

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano. That area is for construction vehicles.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.

  • Weather permitting roads and lots to be milled this week.
  • Hartwick Drive demo continues.
  • Bricks are being installed on the Campus Gateway signs at West Street. Power has been run to the large wall on West Street.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Work on Yager Hall Patio retaining walls to run June 19-July 3.
  • Parking lot between Johnston Science Center and Hilltop/ Oyaron Houses will be milled in its entirety. Please no parking, residents may park at upper Binder PE Center lot.
  • Perrella Health Center Lot, Miller Court and the parking lot adjacent to Elmore Field will be striped for parking on Tuesday, June 27 and Wednesday, June 28. Please, no parking in these areas while lines are laid out and painted.
  • Beginning Friday June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • The townhouse sidewalks will be finished.
  • Installation of a walkway from upper Binder PE Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.

Please note that the work schedule remains weather and equipment dependent.

Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

Campus Map


Past Alerts

06/23/17: Friday

Hartwick Drive is closed and is becoming a pedestrian way.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery immediately behind Clark Hall.  These should be the only vehicles parking in that area.
  • No one should be parking in the area near the old rain garden, near Golisano. That area is for construction vehicles.
  • Download the final design rendering for Hartwick Drive.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.

  • Weather permitting roads and lots to be milled this week.
  • Hartwick Drive demo continues.
  • Bricks are being installed on the Campus Gateway signs at West Street. Power has been run to the large wall on West Street.
  • Saxton Hall and Wilder Hall refurbishment continues.
  • Work on Yager Hall Patio retaining walls to run June 19-July 3.
  • Parking lot between Johnston Science Center and Hilltop/ Oyaron Houses will be milled in its entirety. Please no parking, residents may park at upper Binder PE Center lot.
  • Beginning Friday June 9 enter/exit Bresee Hall from west (hillside) doors or bridge, the front entrance will be excavated.
  • Enter/exit Clark Hall from west doors, Shineman Chapel House side or east (valley side) steps towards Dewar Union, the patio between Bresee Hall and Clark Hall will be excavated.
  • The townhouse sidewalks will be finished.
  • Installation of a walkway from upper Binder PE Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.

06/18/17: Saturday

Hartwick Drive is closed and is becoming a pedestrian way.

Paving, Residence Hall Refurbishments, and the Campus Gateway project continue.

  • Weather permitting roads and lots to be milled this week.
  • Hartwick Drive demo continues.
  • Bricks are being installed on the Campus Gateway signs at West Street. Power has been run to the large wall on West Street.
  • The new water line from Leitzel to Holmes is about 50% complete at this time.
  • The new Townhouse sidewalks are well under way.
  • Saxton and Wilder refurbishment continues.
  • Walk behind Bresee Hall will be poured Saturday, June 17.
  • Work on Yager Hall Patio retaining walls to run June 19-July 3.
  • Parking lot between Johnston Science Center and Hilltop/ Oyaron will be milled in its entirety. Please no parking, residents may park at upper Binder lot.
  • Beginning Friday June 9 enter/exit Bresee from west (hillside) doors or bridge, the front entrance will be excavated.
  • Also enter/exit Clark from west doors, Shineman side or east (valley side) steps towards Dewar, the patio between Bresee and Clark will be excavated.
  • The townhouse sidewalks will be finished.
  • Installation of a walk way from upper Binder PE Center to the new residence hall continues.
  • Do not walk while using ear buds (head phones) around work zones.

06/13/17: Tuesday

Hartwick Drive remains closed to vehicle traffic as work continues.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery behind Clark Hall.
  • Parking will be available at Shineman lot and Greenhouse to new residence hall for Johnstone Science Center, Golisanao Hall, Bresee Hall, Clark Hall and Shineman Chapel House.
  • Parking in Anderson Center, upper and lower Yager lots are unaffected at this time.
  • Download the final design rendering for Hartwick Drive.

Paving and the Campus Gateway project continues.

  • Weather permitting roads and lots to be milled this week.
  • Hartwick Drive demo continues.
  • Bricks are being installed on the Campus Gateway signs at West Street. Power has been run to the large wall on West Street.
  • The new water line from Leitzel to Holmes is about 50% complete at this time.
  • Miller Court and the upper Binder PE Center parking lots are milled, graded and ready for paving. One lane will be available for thru traffic.
  • The excavation for a curb along the road from Wright Stadium to Binder PE Center is in progress. There is no parking along this road, one lane will be kept open for traffic flow.
  • The new Townhouse sidewalks are well under way.
  • Saxton and Wilder have been cleared of the old furniture, built in closets and old restroom fixtures. Refurbishment continues in both buildings.
  • Shineman Chapel House steps to Hartwick Drive have been removed.
  • Do not walk while using ear buds (head phones) around work zones.

Items for the week of June 12th include:

  • The front drive and parking area of Perrella Health Center will be paved with the base layer on June 15. (Added 6/14/17)
  • Parking lot between Johnston Science Center and Hilltop/ Oyaron will be milled in its entirety. Please no parking, residents may park at upper Binder lot. (Added 6/15/17)
  • Dewar water will be off Wednesday June 14 from approximately 7 a.m.-11a.m. to connect Dewar to the new water main.
  • Beginning Friday June 9 enter/exit Bresee from west (hillside) doors or bridge, the front entrance will be excavated.
  • Also enter/exit Clark from west doors, Shineman side or east (valley side) steps towards Dewar, the patio between Bresee and Clark will be excavated.
  • Curb installation from Wright Stadium to Binder PE Center will begin. Expect parking to remain unavailable on this road. One lane will be kept open for traffic flow.
  • Paving will begin in Miller Court and the upper Binder PE Center parking lots.
  • The instillation of a new water line from Leitzel to Holmes will be completed.
  • The townhouse sidewalks will be finished.
  • Refurbishment of Saxton and Wilder residence halls will continue. 
  • Installation of a walk way from upper Binder PE Center to the new residence hall continues.

06/12/17: Monday

Hartwick Drive remains closed to vehicle traffic as work continues.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery behind Clark Hall.
  • Parking will be available at Shineman lot and Greenhouse to new residence hall for Johnstone Science Center, Golisanao Hall, Bresee Hall, Clark Hall and Shineman Chapel House.
  • Parking in Anderson Center, upper and lower Yager lots are unaffected at this time.
  • Download the final design rendering for Hartwick Drive.

Paving and the Campus Gateway project continues.

  • Weather permitting roads and lots to be milled this week.
  • Hartwick Drive demo continues.
  • Bricks are being installed on the Campus Gateway signs at West Street. Power has been run to the large wall on West Street.
  • The new water line from Leitzel to Holmes is about 50% complete at this time.
  • Miller Court and the upper Binder PE Center parking lots are milled, graded and ready for paving. One lane will be available for thru traffic.
  • The excavation for a curb along the rode from Wright Stadium to Binder PE Center is in progress. There is no parking along this road, one lane will be kept open for traffic flow.
  • The new Townhouse sidewalks are well under way.
  • Saxton and Wilder have been cleared of the old furniture, built in closets and old restroom fixtures. Refurbishment continues in both buildings.
  • Shineman Chapel House steps to Hartwick Drive have been removed.
  • Do not walk while using ear buds (head phones) around work zones.

Items for the week of June 12th include:

  • Dewar water will be off Monday from approximately 7am-noon to connect the new water service.
  • Beginning Friday June 9 enter/exit Bresee from west (hillside) doors or bridge, the front entrance will be excavated.
  • Also enter/ exit Clark from west doors, Shineman side or east (valley side) steps towards Dewar, the patio between Bresee and Clark will be excavated.
  • Curb installation from Wright Stadium to Binder PE Center will begin. Expect parking to remain unavailable on this road. One lane will be kept open for traffic flow.
  • Paving will begin in Miller Court and the upper Binder PE Center parking lots.
  • The instillation of a new water line from Leitzel to Holmes will be completed.
  • The townhouse sidewalks will be finished.
  • Refurbishment of Saxton and Wilder residence halls will continue. 
  • Installation of a walk way from upper Binder PE Center to the new residence hall continues.

06/05/17: Monday

Hartwick Drive remains closed to vehicle traffic as work continues.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery behind Clark Hall.
  • Parking will be available at Shineman lot and Greenhouse to new residence hall for Johnstone Science Center, Golisanao Hall, Bresee Hall, Clark Hall and Shineman Chapel House.
  • Parking in Anderson Center, upper and lower Yager lots are unaffected at this time.
  • Download the final design rendering for Hartwick Drive.

Paving and the Campus Gateway project continues.

  • Weather permitting roads and lots to be milled this week.
  • Hartwick Drive demo continues.
  • Bricks are being installed on the Campus Gateway signs at West Street. Power has been run to the large wall on West Street.
  • The new water line from Leitzel to Holmes is about 50% complete at this time.
  • Miller Court and the upper Binder PE Center parking lots are milled, graded and ready for paving. One lane will be available for thru traffic.
  • The excavation for a curb along the rode from Wright Stadium to Binder PE Center is in progress. There is no parking along this road, one lane will be kept open for traffic flow.
  • The new Townhouse sidewalks are well under way.
  • Saxton and Wilder have been cleared of the old furniture, built in closets and old restroom fixtures. Refurbishment continues in both buildings.
  • Shineman Chapel House steps to Hartwick Drive have been removed.
  • Do not walk while using ear buds (head phones) around work zones.