Alerts Archive

Archive of Campus Improvements Traffic & Parking Logistics Alerts:

May 2017

Items for the week of May 29th include:

  • Curb installation from Wright Stadium to Binder PE Center will begin. Expect parking to remain unavailable on this road. One lane will be kept open for traffic flow.
  • Paving will begin in Miller Court and the upper Binder PE Center parking lots.
  • The instillation of a new water line from Leitzel to Holmes will be completed.
  • The hill side of Bresee and the patio between Bresee and Clark will be excavated.
  • Brickwork will continue on the Campus Gateway signs.
  • The townhouse sidewalks will be finished.
  • Refurbishment of Saxton and Wilder residence halls will continue. 
  • Installation of a walk way from upper Binder PE Center to the new residence hall will begin.

05/26/17: Friday:

Hartwick Drive remains closed to vehicle traffic as work continues.

  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery behind Clark Hall.
  • Parking will be available at Shineman lot and Greenhouse to new residence hall for Johnstone Science Center, Golisanao Hall, Bresee Hall, Clark Hall and Shineman Chapel House.
  • Parking in Anderson Center, upper and lower Yager lots are unaffected at this time.
  • Download the final design rendering for Hartwick Drive.

Paving and the Campus Gateway project continues.

  • Bricks are being installed on the Campus Gateway signs at West Street. Power has been run to the large wall on West Street.
  • The new water line from Leitzel to Holmes is about 50% complete at this time.
  • Miller Court and the upper Binder PE Center parking lots are milled, graded and ready for paving. One lane will be available for thru traffic.
  • The excavation for a curb along the rode from Wright Stadium to Binder PE Center is in progress. There is no parking along this road, one lane will be kept open for traffic flow.
  • The new Townhouse sidewalks are well under way.
  • Saxton and Wilder have been cleared of the old furniture, built in closets and old restroom fixtures. Refurbishment continues in both buildings.
  • Shineman Chapel House steps to Hartwick Drive have been removed.
  • Do not walk while using ear buds (head phones) around work zones.

Items for the week of May 29th include:

  • Curb installation from Wright Stadium to Binder PE Center will begin. Expect parking to remain unavailable on this road. One lane will be kept open for traffic flow.
  • Paving will begin in Miller Court and the upper Binder PE Center parking lots.
  • The instillation of a new water line from Leitzel to Holmes will be completed.
  • The hill side of Bresee and the patio between Bresee and Clark will be excavated.
  • Brickwork will continue on the Campus Gateway signs.
  • The townhouse sidewalks will be finished.
  • Refurbishment of Sxton and Wilder residence halls will continue. 
  • Installation of a walk way from upper Binder PE Center to the new residence hall will begin.

Please note that the work schedule remains weather and equipment dependent.

Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

05/23/17: Tuesday

Work on Hartwick Drive continues in the road and parking lot between the Rain Garden and Shineman Chapel House.

Paving and the Campus Gateway project continues.

As work continues on the Campus Gateway structures, please use caution when entering the campus.

Items for the week of May 22 include:

  • Hartwick Drive is closed to vehicle traffic.
  • Milling has begun at upper Binder PE Center and the large parking lot adjacent to Binder. Please leave these areas open to allow for milling. One lane will be available for thru traffic during milling.
  • Milling along road from Wright Stadium to Binder PE Center will begin, no parking along this road, one lane will be kept open for traffic flow.
  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery behind Clark Hall.
  • Excavation begins at Leitzel for new water main along Hartwick Drive ending at Holmes.
  • Hill side of Bresee and patio between Bresee and Clark will be excavated.
  • Area between Johnstone Science Center and Golisano Hall will be excavated.
  • Shineman Chapel House steps to Hartwick Drive have been removed.
  • Refurbishment has begun at Saxton and Wilder residence halls.
  • Townhouse sidewalk removal has begun.
  • Sidewalk removal in front of the new residence hall will begin.
  • Parking will be available at Shineman lot and Greenhouse to new residence hall for Johnstone Science Center, Golisanao Hall, Bresee Hall, Clark Hall and Shineman Chapel House.
  • Parking in Anderson Center, upper and lower Yager lots are unaffected at this time.
  • Do not walk while using ear buds (head phones) around work zones.
  • The work schedule remains weather and equipment dependent.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

05/19/17: Friday

Work on Hartwick Drive continues in the road and parking lot between the Rain Garden and Shineman Chapel House.

Paving and the Campus Gateway project continues.

As work continues on the Campus Gateway structures, please use caution when entering the campus.

Items for the week of May 22 include:

  • Hartwick Drive will be closed to vehicle traffic.
  • Parking has been designated for ADA (near Bresee and Clark), safety vehicles, and package delivery behind Clark Hall.
  • Excavation begins at Leitzel for new water main along Hartwick Drive ending at Holmes.
  • Hill side of Bresee and patio between Bresee and Clark will be excavated.
  • Area between Johnstone Science Center and Golisano Hall will be excavated.
  • Shineman Chapel House steps to Hartwick Drive will be removed.
  • Milling begins at upper Binder PE Center.
  • Milling along road from Wright Stadium to Binder PE Center will begin, no parking along this road, one lane will be kept open for traffic flow.
  • Refurbishment begins at Saxton and Wilder residence halls.
  • Townhouse sidewalk removal will begin.
  • Sidewalk removal in front of the new residence hall will begin.
  • Parking will be available at Shineman lot and Greenhouse to new residence hall for Johnstone Science Center, Golisanao Hall, Bresee Hall, Clark Hall and Shineman Chapel House.
  • Parking in large Binder lot, Anderson Center, upper and lower Yager lots is unaffected at this time.
  • Do not walk while using ear buds (head phones) around work zones.
  • The work schedule remains weather and equipment dependent.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

05/17/17: Wednesday

Work on Hartwick Drive continues in the road and parking lot between the Rain Garden and Shineman Chapel House.

  • The parking lots behind Bresee Hall, Clark Hall and the Rain Garden is closed as construction continues.
  • NO vehicles are allowed behind Bresee/Clark/Rain Garden during construction.
  • Avoid all foot traffic in the Rain Garden.
  • As a result of this, 5 Handicapped Parking spots, 2 Mailroom Pickup spots, 2 Delivery Vehicle Only spots have been relocated from behind Bresee/Clark to new locations on Hartwick Drive. (All new spaces are located between Dewar Union and Memorial Staircase across from Bresee Main entrance.)
  • The 2 Pine Lake Shuttle spots were relocated to a new location on Hartwick Drive to the left of the new footbridge, and all 15-minute Parking spots on Hartwick Drive have been eliminated.
  • Download the map of parking spots on Hartwick Drive.
  • Also, since April 17 through May 28, ALL vehicle traffic is One-Way, from north to south, from the area by Perrella Health Center to the Greenhouse at Johnstone Science Center.
  • Vehicles are not be permitted to enter the roadway by the Greenhouse and drive towards Johnstone and Golisano.
  • Download the final design rendering for Hartwick Drive.

Paving and the Campus Gateway project continues.

As work continues on the Campus Gateway structures, please use caution when entering the campus.

Construction projects for the week of May 22 include:

  • Excavation of water main from Leitzell Hall to Dewar Union.
  • Demo stairs from Shineman Chapel House to Hartwick Drive near footbridge.
  • Demo stairs and patio between Bresee Hall and Clark Hall, these are the stairs on the parking lot side, no ground level foot traffic between Clark Hall and Bresee Hall, use the bridge from 3rd floor Clark to 2nd floor Bresee, or go to the front of the buildings.
  • The threshold at the parking lot side (back) of Bresee Hall will be replaced, do not use these doors except in emergency.
  • Do not walk while using ear buds (head phones) around work zones.
  • The work schedule remains weather and equipment dependent.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

05/12/17: Friday

Work on Hartwick Drive continues in the road and parking lot between the Rain Garden and Shineman Chapel House.

  • The parking lots behind Bresee Hall, Clark Hall and the Rain Garden is closed as construction continues.
  • NO vehicles are allowed behind Bresee/Clark/Rain Garden during construction.
  • Avoid all foot traffic in the Rain Garden.
  • As a result of this, 5 Handicapped Parking spots, 2 Mailroom Pickup spots, 2 Delivery Vehicle Only spots have been relocated from behind Bresee/Clark to new locations on Hartwick Drive. (All new spaces are located between Dewar Union and Memorial Staircase across from Bresee Main entrance.)
  • The 2 Pine Lake Shuttle spots were relocated to a new location on Hartwick Drive to the left of the new footbridge, and all 15-minute Parking spots on Hartwick Drive have been eliminated.
  • Download the map of parking spots on Hartwick Drive.
  • Also, since April 17 through May 28, ALL vehicle traffic is One-Way, from north to south, from the area by Perrella Health Center to the Greenhouse at Johnstone Science Center.
  • Vehicles are not be permitted to enter the roadway by the Greenhouse and drive towards Johnstone and Golisano.
  • Download the final design rendering for Hartwick Drive.

Paving and the Campus Gateway project continues.

  • As work continues on the Campus Gateway structures, please use caution when entering the campus.
  • Excavation and site work will begin May 11 to construct a paved walk from Lower Binder PE Center to Wright Stadium. Please use caution as material is removed, walkway base is built, and lighting is installed. Commuter parking is limited as excavation continues on May 12.
  • During the week of May 8, excavation will begin where the Johnstone Science Center to Binder PE Center stairs were removed.
  • Do not walk while using ear buds (head phones) around work zones.
  • The work schedule remains weather and equipment dependent.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

05/10/17: Wednesday

Work on Hartwick Drive continues in the road and parking lot between the Rain Garden and Shineman Chapel House.

  • The parking lots behind Bresee Hall, Clark Hall and the Rain Garden is closed as construction continues.
  • NO vehicles are allowed behind Bresee/Clark/Rain Garden during construction.
  • Avoid all foot traffic in the Rain Garden.
  • As a result of this, 5 Handicapped Parking spots, 2 Mailroom Pickup spots, 2 Delivery Vehicle Only spots have been relocated from behind Bresee/Clark to new locations on Hartwick Drive. (All new spaces are located between Dewar Union and Memorial Staircase across from Bresee Main entrance.)
  • The 2 Pine Lake Shuttle spots were relocated to a new location on Hartwick Drive to the left of the new footbridge, and all 15-minute Parking spots on Hartwick Drive have been eliminated.
  • Download the map of parking spots on Hartwick Drive.
  • Also, since April 17 through May 28, ALL vehicle traffic is One-Way, from north to south, from the area by Perrella Health Center to the Greenhouse at Johnstone Science Center.
  • Vehicles are not be permitted to enter the roadway by the Greenhouse and drive towards Johnstone and Golisano.
  • Download the final design rendering for Hartwick Drive.

Paving and the Campus Gateway project continues.

  • As work continues on the Campus Gateway structures, please use caution when entering the campus.
  • Excavation and site work will begin May 11 to construct a paved walk from Lower Binder PE Center to Wright Stadium. Please use caution as material is removed, walkway base is built, and lighting is installed.
  • During the week of May 8, excavation will begin where the Johnstone Science Center to Binder PE Center stairs were removed.
  • Do not walk while using ear buds (head phones) around work zones.
  • The work schedule remains weather and equipment dependent.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

05/09/17: Tuesday

Hartwick Drive, at the north entrance, will be blocked by a concrete truck pouring the new wall at Shineman Chapel House from 4-5 p.m. today 05/09/17.

Work on Hartwick Drive continues in the road and parking lot between the Rain Garden and Shineman Chapel House.

  • The parking lots behind Bresee Hall, Clark Hall and the Rain Garden is closed as construction continues.
  • NO vehicles are allowed behind Bresee/Clark/Rain Garden during construction.
  • Avoid all foot traffic in the Rain Garden.
  • As a result of this, 5 Handicapped Parking spots, 2 Mailroom Pickup spots, 2 Delivery Vehicle Only spots have been relocated from behind Bresee/Clark to new locations on Hartwick Drive. (All new spaces are located between Dewar Union and Memorial Staircase across from Bresee Main entrance.)
  • The 2 Pine Lake Shuttle spots were relocated to a new location on Hartwick Drive to the left of the new footbridge, and all 15-minute Parking spots on Hartwick Drive have been eliminated.
  • Download the map of parking spots on Hartwick Drive.
  • Also, since April 17 through May 28, ALL vehicle traffic is One-Way, from north to south, from the area by Perrella Health Center to the Greenhouse at Johnstone Science Center.
  • Vehicles are not be permitted to enter the roadway by the Greenhouse and drive towards Johnstone and Golisano.
  • Download the final design rendering for Hartwick Drive.

Paving and the Campus Gateway project continues.

  • As work continues on the Campus Gateway structures, please use caution when entering the campus.
  • The base layer pavement installation, originally scheduled for Tuesday, May 9, has been moved to Wednesday, May 10. Paving will be behind Shineman Chapel House, Clark Hall and  Bresee Hall, extending to the north end of Golisano Hall and expanded parking into the former Rain Garden site.
  • During the week of May 8, excavation will begin where the Johnstone Science Center to Binder PE Center stairs were removed.
  • Do not walk while using ear buds (head phones) around work zones.
  • The work schedule remains weather and equipment dependent.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

05/08/17: Monday

Work on Hartwick Drive continues in the road and parking lot between the Rain Garden and Shineman Chapel House.

  • The parking lots behind Bresee Hall, Clark Hall and the Rain Garden is closed as construction continues.
  • NO vehicles are allowed behind Bresee/Clark/Rain Garden during construction.
  • Avoid all foot traffic in the Rain Garden.
  • As a result of this, 5 Handicapped Parking spots, 2 Mailroom Pickup spots, 2 Delivery Vehicle Only spots have been relocated from behind Bresee/Clark to new locations on Hartwick Drive. (All new spaces are located between Dewar Union and Memorial Staircase across from Bresee Main entrance.)
  • The 2 Pine Lake Shuttle spots were relocated to a new location on Hartwick Drive to the left of the new footbridge, and all 15-minute Parking spots on Hartwick Drive have been eliminated.
  • Download the map of parking spots on Hartwick Drive.
  • Also, since April 17 through May 28, ALL vehicle traffic is One-Way, from north to south, from the area by Perrella Health Center to the Greenhouse at Johnstone Science Center.
  • Vehicles are not be permitted to enter the roadway by the Greenhouse and drive towards Johnstone and Golisano.
  • Download the final design rendering for Hartwick Drive.

Paving and the Campus Gateway project continues.

  • As work continues on the Campus Gateway structures, please use caution when entering the campus.
  • The base layer pavement will be installed on Tuesday, May 9 behind Shineman Chapel House, Clark Hall and  Bresee Hall, extending to the north end of Golisano Hall and expanded parking into the former Rain Garden site.
  • During the week of May 8, excavation will begin where the Johnstone Science Center to Binder PE Center stairs were removed.
  • Do not walk while using ear buds (head phones) around work zones.
  • The work schedule remains weather and equipment dependent.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

05/05/17: Friday

Work on Hartwick Drive continues in the road and parking lot between the Rain Garden and Shineman Chapel House.

  • The parking lots behind Bresee Hall, Clark Hall and the Rain Garden is closed as construction continues.
  • NO vehicles are allowed behind Bresee/Clark/Rain Garden during construction.
  • Avoid all foot traffic in the Rain Garden.
  • As a result of this, 5 Handicapped Parking spots, 2 Mailroom Pickup spots, 2 Delivery Vehicle Only spots have been relocated from behind Bresee/Clark to new locations on Hartwick Drive. (All new spaces are located between Dewar Union and Memorial Staircase across from Bresee Main entrance.)
  • The 2 Pine Lake Shuttle spots were relocated to a new location on Hartwick Drive to the left of the new footbridge, and all 15-minute Parking spots on Hartwick Drive have been eliminated.
  • Download the map of parking spots on Hartwick Drive.
  • Also, since April 17 through May 28, ALL vehicle traffic is One-Way, from north to south, from the area by Perrella Health Center to the Greenhouse at Johnstone Science Center.
  • Vehicles are not be permitted to enter the roadway by the Greenhouse and drive towards Johnstone and Golisano.
  • Download the final design rendering for Hartwick Drive.

Paving and the Campus Gateway project continues.

  • As work continues on the Campus Gateway structures, please use caution when entering the campus.
  • The base layer pavement will be installed on Thursday, May 11 behind Shineman Chapel House, Clark Hall and  Bresee Hall, extending to the north end of Golisano Hall and expanded parking into the former Rain Garden site.
  • During the week of May 8, excavation will begin where the Johnstone Science Center to Binder PE Center stairs were removed.
  • Do not walk while using ear buds (head phones) around work zones.
  • The work schedule remains weather and equipment dependent.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

April 2017

04/28/17: Friday

Work on Hartwick Drive began on Monday, April 17 in the road and parking lot between the Rain Garden and Shineman Chapel House.

  • The parking lots behind Bresee Hall, Clark Hall and the Rain Garden is closed as construction continues.
  • NO vehicles are allowed behind Bresee/Clark/Rain Garden during construction.
  • Avoid all foot traffic in the Rain Garden.
  • As a result of this, 5 Handicapped Parking spots, 2 Mailroom Pickup spots, 2 Delivery Vehicle Only spots have been relocated from behind Bresee/Clark to new locations on Hartwick Drive. (All new spaces are located between Dewar Union and Memorial Staircase across from Bresee Main entrance.)
  • The 2 Pine Lake Shuttle spots were relocated to a new location on Hartwick Drive to the left of the new footbridge, and all 15-minute Parking spots on Hartwick Drive have been eliminated.
  • Download the map of parking spots on Hartwick Drive.
  • Also, since April 17 through May 28, ALL vehicle traffic is One-Way, from north to south, from the area by Perrella Health Center to the Greenhouse at Johnstone Science Center.
  • Vehicles are not be permitted to enter the roadway by the Greenhouse and drive towards Johnstone and Golisano.
  • Download the final design rendering for Hartwick Drive.

Paving and the Campus Gateway project continues.

  • As work continues on the Campus Gateway structures, please use caution when entering the campus.
  • On Monday, May 1 the lower section of wooden steps from Johnstone Science Center to Binder PE Center will be removed, a temporary gravel walk way will be installed to allow access to the remaining steps.
  • Also on Monday, May 1, the lower section of steps from Shineman Chapel House to Hartwick Drive will be removed to install the foundation of the new sidewalk from Shineman parking lot. The upper walk in front of Shineman Chapel House to Clark Hall will not be affected.
  • Thursday, May 4 the Bresee and Clark lot will be milled, the base layer pavement will be installed in time for commencement activity parking.
  • Work at the Charlotte side of Smith Hall will conclude early in the week of May 1.
  • The sidewalk behind Bresee and Clark is scheduled for Monday, May 1 and Tuesday, May 2.
  • Do not walk while using ear buds (head phones) around work zones.
  • The work schedule remains weather and equipment dependent.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

04/27/17: Thursday

Work on Hartwick Drive began on Monday, April 17 in the road and parking lot between the Rain Garden and Shineman Chapel House.

  • The parking lots behind Bresee Hall, Clark Hall and the Rain Garden is closed as construction continues.
  • NO vehicles are allowed behind Bresee/Clark/Rain Garden during construction.
  • Avoid all foot traffic in the Rain Garden.
  • As a result of this, 5 Handicapped Parking spots, 2 Mailroom Pickup spots, 2 Delivery Vehicle Only spots have been relocated from behind Bresee/Clark to new locations on Hartwick Drive. (All new spaces are located between Dewar Union and Memorial Staircase across from Bresee Main entrance.)
  • The 2 Pine Lake Shuttle spots were relocated to a new location on Hartwick Drive to the left of the new footbridge, and all 15-minute Parking spots on Hartwick Drive have been eliminated.
  • Download the map of parking spots on Hartwick Drive.
  • Also, since April 17 through May 28, ALL vehicle traffic is One-Way, from north to south, from the area by Perrella Health Center to the Greenhouse at Johnstone Science Center.
  • Vehicles are not be permitted to enter the roadway by the Greenhouse and drive towards Johnstone and Golisano.
  • Download the final design rendering for Hartwick Drive.

Paving and the Campus Gateway project continues.

  • As work continues on the Campus Gateway structures, please use caution when entering the campus.
  • Do not walk while using ear buds (head phones) around work zones.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

04/17/17: Monday

Work on Hartwick Drive begins Monday, April 17 in the road and parking lot between the Rain Garden and Shineman Chapel House.

  • The parking lots behind Bresee Hall, Clark Hall and the Rain Garden will be closed as construction begins.
  • NO vehicles will be allowed behind Bresee/Clark/Rain Garden once construction begins.
  • As a result of this, 5 Handicapped Parking spots, 2 Mailroom Pickup spots, 2 Delivery Vehicle Only spots have been relocated from behind Bresee/Clark to new locations on Hartwick Drive. (All new spaces are located between Dewar Union and Memorial Staircase across from Bresee Main entrance.)
  • The 2 Pine Lake Shuttle spots were relocated to a new location on Hartwick Drive to the left of the new footbridge, and all 15-minute Parking spots on Hartwick Drive have been eliminated.
  • Download the map of parking spots on Hartwick Drive.
  • Also, from April 17 through May 28, ALL vehicle traffic will flow One-Way, from north to south, from the area by Perrella Health Center to the Greenhouse at Johnstone Science Center.
  • Vehicles will not be permitted to enter the roadway by the Greenhouse and drive towards Johnstone and Golisano.
  • Download the final design rendering for Hartwick Drive.

Paving and the Campus Gateway project continues.

  • Work to replace the upper entrance sidewalk and pad of the Binder Physical Education Building began on Monday, April 10. Continue to use side doors to enter the building.
  • Brick will arrive Monday, April 17 for the Campus Gateway structures. As work continues, please use caution when entering the campus.
  • The retaining wall in front of Smith Hall is being replaced.
  • Work at the Rain Garden has begun. Expect heavy truck traffic as material is removed in the Rain Garden area.
  • Avoid all foot traffic in the Rain Garden.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

04/14/17: Friday

Work on Hartwick Drive begins Monday, April 17 in the road and parking lot between the Rain Garden and Shineman Chapel House.

  • The parking lots behind Bresee Hall, Clark Hall and the Rain Garden will be closed as construction begins.
  • NO vehicles will be allowed behind Bresee/Clark/Rain Garden once construction begins.
  • As a result of this, 5 Handicapped Parking spots, 2 Mailroom Pickup spots, 2 Delivery Vehicle Only spots have been relocated from behind Bresee/Clark to new locations on Hartwick Drive. (All new spaces are located between Dewar Union and Memorial Staircase across from Bresee Main entrance.)
  • The 2 Pine Lake Shuttle spots were relocated to a new location on Hartwick Drive to the left of the new footbridge, and all 15-minute Parking spots on Hartwick Drive have been eliminated.
  • Download the map of parking spots on Hartwick Drive.
  • Also, from April 17 through May 28, ALL vehicle traffic will flow One-Way, from north to south, from the area by Perrella Health Center to the Greenhouse at Johnstone Science Center.
  • Vehicles will not be permitted to enter the roadway by the Greenhouse and drive towards Johnstone and Golisano.
  • Download the final design rendering for Hartwick Drive.

Paving and the Campus Gateway project continues.

  • Work to replace the upper entrance sidewalk and pad of the Binder Physical Education Building began on Monday, April 10. Continue to use side doors to enter the building.
  • Brick will arrive Monday, April 17 for the Campus  Gateway structures. As work continues, please use caution when entering the campus.
  • The retaining wall in front of Smith Hall is being replaced.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

04/11/17: Tuesday

  • Traffic and parking on campus will change, as was indicated on 04/05/17, on Monday, April 17.
  • Work will begin Monday, April 17, in the rain garden and road/parking lot behind Bresee and Clark.
  • The contractor will park an excavator in the rain garden tomorrow, Wednesday April 12, in anticipation of starting the work next Monday.
  • Power to the rain garden lights will be disconnected on Thursday, April 13.
  • Work to replace the upper entrance sidewalk and pad of the Binder Physical Education Building began on Monday, April 10. Continue to use side doors to enter the building.
  • Work will continue on the Campus Gateway. Please use caution entering campus.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

04/08/17: Saturday

  • Due to weather conditions, the construction work scheduled for Hartwick Drive will not begin until Monday, April 17.
  • Traffic and parking on campus will not change, as was indicated on 04/05/17, until Monday, April 17.
  • Work will continue on the Campus Gateway.
  • Work to replace the upper entrance sidewalk and pad of the Binder Physical Education Building will begin on Monday, April 10. Use side doors to enter the building.
  • Please use caution entering campus.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

04/06/17: Thursday

  • Due to weather conditions, the construction work scheduled for Hartwick Drive will not begin until Monday, April 17.
  • Traffic and parking on campus will not change, as was indicated on 04/05/17, until Monday, April 17.
  • Work will continue on the Campus Gateway.
  • Please use caution entering campus.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

04/05/17: Wednesday

Work on Hartwick Drive begins Monday, April 10 in the road and parking lot between the Rain Garden and Shineman Chapel House.

  • The parking lots behind Bresee Hall, Clark Hall and the Rain Garden will be closed as construction begins.
  • NO vehicles will be allowed behind Bresee/Clark/Rain Garden once construction begins.
  • As a result of this, 5 Handicapped Parking spots, 2 Mailroom Pickup spots, 2 Delivery Vehicle Only spots have been relocated from behind Bresee/Clark to new locations on Hartwick Drive. (All new spaces are located between Dewar Union and Memorial Staircase across from Bresee Main entrance.)
  • The 2 Pine Lake Shuttle spots were relocated to a new location on Hartwick Drive to the left of the new footbridge, and all 15-minute Parking spots on Hartwick Drive have been eliminated.
  • Download the map of parking spots on Hartwick Drive.
  • Also, from April 10 through May 21, ALL vehicle traffic will flow One-Way, from north to south, from the area by Perrella Health Center to the Greenhouse at Johnstone Science Center.
  • Vehicles will not be permitted to enter the roadway by the Greenhouse and drive towards Johnstone and Golisano.

Anticipated construction schedule is weather dependent:

  • April 10-11 Remove lights, trees and sculpture; sculpture, benches, plaques reserved for reuse.
  • April 12-18 Install underground infrastructure.
  • April 19-21 Mill asphalt, fill, site preparation.
  • April 24-27 Install curb.
  • April 27- May 5 Complete final site prep and install binder course to allow parking for Commencement.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

04/04/17: Tuesday

  • Campus Gateway construction will continue at the West Street steps, adjacent to the Anderson Center for the Arts, on Wednesday, April 5, 2017.
  • These steps will be closed to pedestrian traffic until this phase of construction is finished.
  • Pedestrians, please enter and exit campus at the Clinton Street entrance by the Anderson Center for the Arts parking lot.
  • Please use caution entering campus.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

March 2017

03/30/17: Thursday

  • Hartwick entered the first phase of the Campus Gateway construction at 7a.m. this morning.
  • Construction will continue at the entrance to remove topsoil and grade for new sidewalk entrance.
  • Schedule is to have forms constructed for new gateway signs early next week.
  • Please use caution entering campus.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

03/27/17: Monday

  • Beginning Monday, April 10, 2017, the parking lots behind Bresee Hall, Clark Hall and the Rain Garden will be closed as construction begins.
  • NO vehicles will be allowed behind Bresee/Clark/Rain Garden once construction begins.
  • As a result of this, 5 Handicapped Parking spots, 2 Mailroom Pickup spots, 2 Delivery Vehicle Only spots will be relocated from behind Bresee/Clark to new locations on Hartwick Drive. (All new spaces are located between Dewar Union and Memorial Staircase across from Bresee Main entrance.) 
  • The 2 Pine Lake Shuttle spots will be relocated to a new location on Hartwick Drive to the left of the new footbridge, and all 15-minute Parking spots on Hartwick Drive will be eliminated.
  • Also, from April 10 through May 21, ALL vehicle traffic will flow One-Way, from north to south, from the area by Perrella Health Center to the Greenhouse at Johnstone Science Center.
  • Vehicles will not be permitted to enter the roadway by the Greenhouse and drive towards Johnstone and Golisano.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.

03/15/17: Wednesday

  • Demolition work will begin on the West Street signage/entrance/walls on April 1 or sooner, weather permitting.
  • Work on the parking lot behind Clark Hall, Bresee Hall, and the Arnold Rain Garden will begin April 10,
  • There will be no parking behind Clark, Bresee and the Rain Garden after April 9.
  • Handicapped and Service Vehicle parking behind Clark, Bresee, and the Rain Garden will be moved to Hartwick Drive.
  • Traffic on Hartwick Drive will be one way — from Shineman Chapel House to behind Johnstone Science Center — starting April 9.
  • Questions: Contact the Campus Safety Dispatch Desk at 607-431-4111.